- At 7:47 pm on June 30, we started the Alternative Cooling System of spent
fuel pool of Unit 3. It was under adjustment operation. After performance
evaluation, we brought to a full operation at 11:00 am on July 1.
- At 11:43 am on July 1, we started cleaning up the first floor of reactor
building of Unit 3 using a robot.
- At 10:00 am on July 1, we started transferring low radioactive
accumulated water, which had been removed from turbine building of
Unit 6, from temporary tank to Mega Float.
- At 10:00 am on July 1, we started transferring of accumulated water from
the underground floor of the turbine building of Unit 6 to temporary
tank. "